試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

In the initiation phase of your project, it is apparent that factions within the client's company have significantly different views on how the project should be structured and how the deliverables should be defined. Which of the following is the BEST thing to do?
A、Ask the client when they will be iii agreement on the project requirements.
B、Work with leadership from each area to collaboratively engineer a mutually acceptable solution.
C、Make sure the terms and conditions of the contract are clear.
D、List the consequences of changes in the contract's requirement section.