线人电影在线观看完整版国语,青久在线,爱上女教师完整版电影在线观看,av在线手机版,十诫国语电影在线观看完整版 ,国产凌凌漆电影完整版国语未删减,18被视频免费观看视频

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the planning phase, the project manager estimates task durations based on the availability of the resources. How should the project manager gain commitment from the resources’ providers?
A、 Share the project management plan and human resource management plan to the functional manager.
B、 Send an e-mail to the staffing department with a completed resource request.
C、 Involve the functional managers in developing the plan and obtain their approval.
D、 Assure the functional managers that the resources will be released and completed.


相關(guān)試題

推薦文章