試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Your company is receiving a shipment of goods from the sellers when you get a call from the procurement manager who tells you that the shipment does not meet the requirements of the contract. You look at the shipment yourself and determine that the shipment meets the needs of the project. What should you do next?
A、 Send the shipment back.
B、 Accept the shipment.
C、 Issue a change order to change the contract specifications.
D、 Expect to receive a claim from the seller.